SR 4 single-lane traffic on gas line work

🔊 Listen · narrated by Aiden

Work on a buried gas line extension will cause single-lane traffic between 50th Avenue (milepost 56.4) and 42nd Avenue (milepost 57.2) on SR 4 from Aug. 17 to Oct. 12, 2026.

Travelers in both directions will take turns moving through a single lane weekdays from 7:30 a.m. to 5 p.m. Flaggers will direct traffic through the work zone.

📄 Source: WSDOT — Highway Construction & Closures — https://wsdot.wa.gov/travel/road-construction
Source receipts4 of 4 passages supported · 100%

Automated checks compare the headline, summary and each body passage with the saved source. A checkmark records the model’s assessment; readers can inspect the quote. Source: original document ↗

  • ✓
    SR 4 single-lane traffic on gas line work“004 [4 mi from Longview]: Monday, Aug. 17 through Monday, Oct. 12: Travelers in both directions of SR 4 will take turns moving through a single lane between 50th Avenue (milepost 56.4) and 42nd Avenue (milepost 57.2), weekdays from 7:30 a.m. to 5 p.m., for buried gas line extension work.”
  • ✓
    Work on buried gas line extension will cause single-lane traffic between 50th and 42nd Avenues on SR 4 from Aug. 17 to Oct. 12.“004 [4 mi from Longview]: Monday, Aug. 17 through Monday, Oct. 12: Travelers in both directions of SR 4 will take turns moving through a single lane between 50th Avenue (milepost 56.4) and 42nd Avenue (milepost 57.2), weekdays from 7:30 a.m. to 5 p.m., for buried gas line extension work.”
  • ✓
    Work on a buried gas line extension will cause single-lane traffic between 50th Avenue (milepost 56.4) and 42nd Avenue (milepost 57.2) on SR 4 from Aug. 17 to Oct. 12, 2026.“004 [4 mi from Longview]: Monday, Aug. 17 through Monday, Oct. 12: Travelers in both directions of SR 4 will take turns moving through a single lane between 50th Avenue (milepost 56.4) and 42nd Avenue (milepost 57.2), weekdays from 7:30 a.m. to 5 p.m., for buried gas line extension work.”
  • ✓
    Travelers in both directions will take turns moving through a single lane weekdays from 7:30 a.m. to 5 p.m. Flaggers will direct traffic through the work zone.“Travelers in both directions of SR 4 will take turns moving through a single lane between 50th Avenue (milepost 56.4) and 42nd Avenue (milepost 57.2), weekdays from 7:30 a.m. to 5 p.m., for buried gas line extension work. Flaggers will direction travelers through the area.”
Source text saved for this check (2026-10-11T12:47:06.876Z)
WSDOT highway construction and road closures within 50 miles of Longview — 10/11/2026:

004 [4 mi from Longview]: Monday, Aug. 17 through Monday, Oct. 12: Travelers in both directions of SR 4 will take turns moving through a single lane between 50th Avenue (milepost 56.4) and 42nd Avenue (milepost 57.2), weekdays from 7:30 a.m. to 5 p.m., for buried gas line extension work. 

Flaggers will direction travelers through the area. Plan ahead and expect delays.
Effective: Aug 17, 2026, 5:00 AM
Expected end: Oct 12, 2026, 5:00 PM

006 [34 mi from Longview]: Monday, Sept. 14 through Friday, Oct. 16: Travelers in both directions of SR 6 will take turns moving through a single lane between Clinton Road (milepost 45.6) and Twin Oaks Road (milepost 46.5), weekdays from 7 a.m. to 3:30 p.m., for work to replace a buried water main line. 

Flaggers will direct travelers through the work zone. Plan ahead and expect delays. 

This work is being done by Boistfort Valley Water Corporation.
Effective: Sep 14, 2026, 5:00 AM
Expected end: Oct 16, 2026, 3:30 PM